Intro
Scaffold and landing structure for water tower restoration and painting. Transfield/ Melbourne Water asked Swiftscaff to design and install scaffold to their outlet structure in the middle of the Reservoir which was a mission in itself.
Solution
We had to construct a temporary barge to support stillage’s of Scaffold while we craned them on and towed it to the structure which was a very slow procedure requiring six days. To further assist, we added a landing platform for painters and workers to arrive by boat and transfer safely with their tools and equipment.
System
Swiftscaff can help solve difficult scaffolding problems with economical solutions. Whether the scaffold is required for construction, maintenance or a shutdown, our Layher scaffolding system provides a stronger, faster and most importantly, safer solution.